Arthur Yuenger, Architect

 

Arthur Yuenger, Architect
2000 N. Court Suite 9K
Fairfield, IA 52556
641-470-1428
 
art@arthuryuenger.com
 

Member of NCARB
(National Council of Architectural Registration Boards)


Maharishi Sthapatya
Veda® architect

 

   
 

Dwelling Unit Addition — Aspen, Colorado — 2001

Previous Home Next
 
       

Objective: construct a "simple" two-bedroom addition to the existing house.

Special challenges: determining the available floor area (as related to the allowable floor area determined from the property floor area ratio) applicable to the floor area of the addition.

Additional Information:
The addition proved to be far from simple. Instead it was extremely complex because of the restrictions imposed by the limited available floor area.

A complicated, lengthy review of the City of Aspen Zoning Code (to verify the allowable floor area of the existing house including the addition) determined that 370 square feet was available for the expansion of the total existing floor area. [The total allowable floor area of the house including the addition was a function (in part) of the exterior wall area below grade of both the existing and proposed addition, corresponding to the actual floor area of the house including the addition.]

The addition could be constructed only if the existing basement mechanical room was relocated, and the basement renovated to include a guest bedroom and bath accessible from inside the existing house, but with a new required exit door to grade. The determination of the available floor area was complicated because the surface area of the exterior renovated basement wall at the new lightwell affected the included floor area that could be applied to the basement.

One bedroom with an adjoining bath occupies the first level of the addition. A new basement and crawl space (constructed below the first level) adjoins the existing renovated basement under the north wing. (The north wing is the portion of the house on the extreme right in the photographs of the exterior.)

Because of the floor area limitations, the enclosure at the upper level of the existing spiral stair could not be modified. This meant that the spiral stair had to be incorporated into the new design. Fortunately the existing spiral stair was constructed as a kit enabling the direction of the spiral to be reversed to accommodate the circulation flow at the middle landing of the stair as related to the adjacent hall to the bedroom. Another new stair section was added below the existing portion to provide access to the basement. As simple as the stair extension appears it was not easy because the interior sheetrock enclosure had to continue in an uninterrupted plane from the upper level wood wall framing (which could not be altered) to the basement level concrete wall (which also could not be altered). Careful manipulation of the wall surface framing by the very savvy job superintendent enabled this to happen.

The basement renovation required new openings cut into the existing reinforced concrete foundation. The existing concrete slab was removed, and a new slab (whose elevation had to correspond to the accumulated riser heights of the spiral stair) was constructed at an elevation below the footing of the existing foundation wall (requiring underpinning of, and reinforcement to, the existing footing).

The bottom left photograph shows the state-of-the-art glass and tile shower (and adjoining tub) accessed at the basement level guest bedroom. The bottom right photograph shows the reversed, upper portion of the existing spiral stair at the first floor landing where the new portion of the stair continues to the basement level.

The general contractor was Rudd Construction. The addition was constructed at approximately the same cost as Rudd's original estimate of $350,000. Interestingly, because of the inflated value of homes in Aspen, it was less expensive for the owners to build the addition than to purchase another larger house.

The successful completion of this project was the result of, (1) decisions based on my knowledge of design as related to construction details, (2) a comprehensive set of architectural drawings that included the complex floor area calculations, (3) on-site decisions made by a very talented job superintendent, (4) interior appointments including bath furnishings and cabinetry selected and coordinated by a knowledgeable project manager, and (5) no insurmountable excavation surprises occurring during construction (such as an excavated boulder rolling into the adjacent house, or the shifting of a foundation wall during underpinning). Careful coordination between myself and the contractors representatives was maintained via phone conversations, faxes and several site visitations.

 
 
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
       
         
 

PORTFOLIO      |      MY SERVICES      |      ABOUT ME      |      HOME

 
 
Copyright © 2006 Arthur Yuenger. All Rights Reserved.
Website by Eric Randall